CONFIDENTIAL HYPERSCALE DATA CENTER.
PROJECT NAME.
Temporary Industrial Water Pumping System
CUSTOMER.
Confidential Client
MARKET SECTOR.
Data Center
SERVICES.
Modular MEP Design
Offsite Fabrication
THE CHALLENGE.
- Maintaining a fast paced, phased, start-up and testing schedule.
- Filling the need for temporary system redundancy before permanent back-up systems could be installed.
THE SOLUTION.
Limbach Collaborative Services (LCS) designed and Limbach Company fabricated and installed a portable, temporary, Industrial Water pumping and storage system in a shipping container that could be utilized at various locations and times on the project site as necessary.