CONFIDENTIAL HYPERSCALE DATA CENTER.

PROJECT NAME.

Temporary Industrial Water Pumping System

CUSTOMER.

Confidential Client

MARKET SECTOR.

Data Center

SERVICES.

Modular MEP Design

Offsite Fabrication

THE CHALLENGE.

  • Maintaining a fast paced, phased, start-up and testing schedule.
  • Filling the need for temporary system redundancy before permanent back-up systems could be installed.

THE SOLUTION.

Limbach Collaborative Services (LCS) designed and Limbach Company fabricated and installed a portable, temporary, Industrial Water pumping and storage system in a shipping container that could be utilized at various locations and times on the project site as necessary.