PROVIDING SCHEDULE & BUDGET
CONTROL FOR THE NEW
MCLAREN GREATER LANSING HOSPITAL.

PROJECT NAME.

McLaren Greater Lansing Hospital

CUSTOMER.

Mclaren Healthcare & Barton Malow / Christman Joint Venture

MARKET SECTOR.

Healthcare

SERVICES.

MEP Engineering Peer Review

Preconstruction Services

Virtual Design & Construction

Building Information Modeling (BIM)

Prefabrication

Mechanical and Plumbing Construction

Building Controls

THE CHALLENGE.

Taking off-site prefabrication further than ever before to improve quality, onsite safety, and project schedule.

THE SOLUTION.

All horizontal domestic and heating piping was prefabricated off-site which eliminated more than 40% of the field labor installation hours

  • 3,000 linear ft of prefabricated racks
  • Full 9 stories mechanical shaft piping installed in 1 day
  • Prefabrication reduced manpower on-site by 20 people
  • Benefits also include trimming an anticipated 2 months off the schedule which saved the owner 5.6M